2020: Construction of the Apartments

In 2020, the construction of the apartments on the first floor finally began. A company built the bathroom walls and the partition walls between the apartments. These are relatively small spaces with many corners, which meant a lot of work. Due to COVID-19, work could not continue consistently, and some construction materials were temporarily unavailable. However, by the end of the year, the walls, floors, and ceilings were finished, and I could start tiling the bathrooms.

Also, in 2020, a new electrical connection was installed, and a new electrical panel was set up.